Once the job budget has been entered in Business Central, the values from the Budget (Total Cost) and Budget (Total Price) can be saved as Original or Current budget.
Actions
Create original budget
Create original budget the values from the project planning lines are transferred to the columns Original budget Total Cost and Original budget Total Price as well as to the columns Current budget Total Cost and Current budget Total Price.
Delete original budget
Delete original budget the values can be removed from all columns. This function can only be used until the first time a (separate) current budget is created.
Change original budget
Original budget Change items are written to the original budget and the current budget.
Change Budget
Budget change items are only created for the Current Budget, but not for the Original Budget. Once this function has been executed, the original budget cannot be changed or deleted.